+90 0532 157 29 65

Kromko Mining

Project Details

Project Date:

Oca 2012

Client:

Kromko Madencilik

Category:

Mining

Location:

Eskişehir

We present our approach to the chrome mine project in Alpu, Eskisehir, targeting extensive installations and capacity expansion. Details of this project are listed below:

Kromko Mining Installation:

* 24 shaking tables
* 1 dragon table
* 2 mills
* 6 sieves
* 3 hydrosizer
* 7 mud pumps
* Waste Disposal Tank
* Transformer Installation
These extensive installations and transformer installation were meticulously carried out with the aim of making the operation of the chrome mine efficient and increasing productivity.

Kromko Mining Transformer Installation:

Within the scope of our project, a transformer was also installed to meet the power requirements of the facility and to regulate the electric current. This transformer is of great importance in effectively meeting the energy needs of the facility so that it can operate uninterruptedly and reliably.

    • Electrical and Automation, Technical and Training Support: We emphasize our important role in the project in providing electrical automation, technical support and training services. The electrical automation system was meticulously designed and implemented to make the plant run more effectively and smoothly. Our technical support team was actively involved to ensure that processes ran smoothly and efficiently. Mine personnel received comprehensive training on how to effectively use the plant’s new equipment and optimize operations. The Eskisehir Alpu Chrome Mine project aims to make the operation of the mine more productive with extensive installations, capacity increase and transformer installation. We are pleased to emphasize that the electrical, automation, technical and training support we provided in the project contributed to the goal of increasing the performance of the facility and strengthening the competitiveness of the business.